GRIDCO is seeking a consultant to assess the environmental and social impacts of the proposed 225 MW Upper Indravati floating solar-BESS project and its evacuation infrastructure. Image Credit/Source: Christian Agbede/Unsplash  
Markets

GRIDCO seeks ESIA consultant for 225 MW floating solar-BESS

Kaleeswari

Executive Summary

GRIDCO Limited has invited consultants to conduct an Environmental and Social Impact Assessment (ESIA) for the proposed 225 MW Upper Indravati floating solar and battery energy storage project in Odisha. The assignment includes the evacuation infrastructure and associated transmission lines. The tender was issued on 16 October 2026. A pre-bid meeting is scheduled for 30 October, while bids close on 17 November 2026. 

 Snapshot 

  • Tendering authority: GRIDCO Limited 

  • Tender reference: GRIDCO/RENA/E-Tender/04/2026-27 

  • Project: Upper Indravati floating solar and BESS 

  • Solar capacity: 225 MW 

  • Location: Upper Indravati, Odisha, India 

  • Tender scope: ESIA consultancy, evacuation infrastructure and transmission lines 

  • Key dates: Pre-bid meeting 30 October; bid deadline 17 November 2026 

Odisha government-owned power company GRIDCO Limited has invited bids from consultancy firms for an Environmental and Social Impact Assessment of the proposed 225 MW Upper Indravati floating solar and battery energy storage project. The tender also covers the project's power evacuation infrastructure and associated transmission lines.  

The e-tender was issued on 16 October 2026 under reference GRIDCO/RENA/E-Tender/04/2026-27. It is a consultancy procurement linked to the proposed floating solar and storage development at Upper Indravati. The tender identifies a BESS component but does not state its power or energy rating.  

The selected consultant will assess the project's environmental and social impacts, examine related risks and recommend mitigation measures.  

The study is expected to cover potential effects on the reservoir environment, nearby communities and existing activities around the project area.  

GRIDCO serves as Odisha's nodal agency for renewable energy under the Odisha Renewable Energy Policy, 2022.  

The request for proposal and bidding requirement is available through GRIDCO's website and the designated e-tender portal.  

The pre-bid meeting is scheduled for 30 October 2026 at 11:00 AM at GRIDCO's conference hall, with virtual participation available. Online bids are due by 3:00 PM on 17 November 2026.  

Techno-commercial bids are scheduled to open at 5:00 PM on 17 November. GRIDCO said amendments and clarifications will be published on its website and the e-tender portal. 

The tender is for an ESIA consultant. It is not a construction award for the solar-plus-storage project.  

AMEA Power signs deals for 1 GWh BESS in Uzbekistan

Sahaj Solar to set up 1.8 GWh BESS factory in Gujarat, India

ACME Solar signs 300 MW/1,200 MWh SECI FDRE PPA at INR 6/unit

ENGIE secures financial close for 150 MW Hazelwood BESS expansion

HiTHIUM surpasses 200 GWh in global battery shipments