The Linyi Huazhen storage station in Shandong has reached full capacity, now that its 20 MW / 80 MWh second phase has been connected. That phase, which was built by Chenlong Holdings Group, is cooled by immersion. Its supplier, Haixi New Energy, has called it the first commercial use of the technology at a large station in the province.

Chenlong Holdings Group, a China-based investor in energy storage, has brought its Linyi Huazhen independent storage station in Shandong province to full capacity. The station's second phase, a 20 MW / 80 MWh system, was connected to the grid on 19 November. It has joined a first phase of 180 MW / 360 MWh, which had been connected on 22 June 2026, and the station is operated by Huazhen New Energy.

The second phase differs from the first in the way that it is cooled. In it, the lithium iron phosphate (LFP) cells sit wholly submerged in an insulating coolant, while the first phase has been fitted with conventional liquid cooling. The core equipment and the complete system were supplied by Haixi New Energy, which has developed the immersion technology itself. The company has described the project as the first commercial use of immersion cooling at a large centralised storage station in Shandong.

Haixi has also set out what the design is expected to achieve. It has said that the coolant holds the temperature difference between the cells within 3°C, and that the cycle life is thereby extended by more than 20%. Because the cells are kept from contact with air, the thermal runaway suppression efficiency is said to be 85% higher. Since air ducts and cold plates are no longer required, the company has added, the energy density of the system is 20% higher.

With both phases in service, the station is expected to charge and discharge about 150 million kWh a year. That capacity will be used for peak regulation, frequency regulation and reserve services on the Shandong grid, so that surplus solar power can be absorbed at midday and returned during the evening peak. The station is connected through its own 220 kV step-up substation to a State Grid substation, and it has been listed by Linyi city among its key independent storage demonstration projects. Chenlong has said that it will draw on the station's operation to develop a sustainable business model for independent storage.

Projects of this kind are being added to the largest battery fleet in the world. According to Ember, China's installed lithium-ion BESS capacity was approaching 150 GW by the first quarter of 2026, and 18.76 GW / 65.46 GWh was commissioned in December 2025 alone. Ember has argued, however, that the greater task now lies in making fuller use of those batteries.