Squadron's 1 GW Cullen Bullen battery enters NSW planning

Karthik S Gannavaram

Executive summary

The proposed 1 GW Cullen Bullen Battery of Squadron Energy, which is to hold up to eight hours of storage, has entered the planning system of New South Wales. Its scoping report has been placed on the NSW Planning Portal, and the views of the local community near Lithgow are now being sought.

  • Power: 1 GW

  • Duration: 8 hours

  • Grid link: 500 kV

  • Network owner: Transgrid

  • Council area: Lithgow

  • Planning stage: Awaiting SEARs

Squadron Energy, an Australia-based renewable energy company, said on 24 November that the scoping report for its Cullen Bullen Battery had been placed on the NSW Planning Portal. The battery has been proposed at 1 GW, and its site lies some 25 km north of Lithgow, or 175 km west of Sydney.

Up to eight hours of storage is proposed, with a direct tie-in to the existing 500 kV network of Transgrid at the site. Energy would be stored at times of plenty and given back when it is needed, so that the supply can be kept reliable.

The project is at an early stage, and Squadron is seeking feedback from the local community to help inform its design.

We want to hear from local residents and businesses as we develop this proposal, understand what matters to them and identify opportunities for the project to benefit the wider community.
Sean Cross, Project Developer at Squadron Energy

Early engagement with the community and lasting local benefits have been named by Mr Cross as the priorities of the company. To that end, Squadron has promised investment in infrastructure, funding for community programmes and the creation of local jobs and training. Its sponsorship programme is already open to organisations in education, community development, health and the environment. Besides Cullen Bullen, the company is also developing the Gol Gol Battery and firming power stations at Dubbo and in the Illawarra.

At eight hours, the battery would run for far longer than the large batteries that are already in service in the state. The 415 MW/1,660 MWh Orana BESS near Wellington stores four hours of power, while the 850 MW Waratah Super Battery, which reached full operation in September, stores 1,680 MWh. The largest battery in Australia, at Eraring, is being expanded to 700 MW and 3,160 MWh.

HEXA receives financing for 90 MW (AC) BESS projects in Japan

InCommodities signs seven-year deal for 250 MWh Finnish BESS

Peak Energy lifts Series B to $157 million for sodium-ion BESS

L&T wins 300 MW/900 MWh liquid-cooled BESS order at Khavda