AFRY has been awarded the Phase II consultancy for the Raudsepa battery of 192 MW and 420 MWh in southern Estonia, which has now moved into construction. Under the award, the company is to manage and supervise the works until the third quarter of 2027, after which the battery is to be tested before it enters commercial operation.
Click here for a quick project snapshot
AFRY, a Sweden-based engineering and consulting company, has been awarded the Phase II consultancy services for the Raudsepa BESS in southern Estonia. The battery has been rated at 192 MW of power and 420 MWh of capacity, and its construction has now begun. The award was announced by AFRY on 24 November.
Under the Phase II scope, AFRY is to act as the construction project manager of the battery. Its work takes in detailed engineering reviews, the supervision of construction and of health, safety, environment and quality (HSEQ), and technical advice for as long as the works go on. The new role follows a first phase, in which AFRY had given its support to the project before the final investment decision was taken.
That supervision is to last for the whole of the construction phase, which has been estimated to run until the third quarter of 2027. A period of testing and quality assurance is then to follow, before the battery enters commercial operation. When the investment was announced in September, Taaleri Energia had said that the works were to start that month and that the battery was expected to be fully operational by November 2027.
The project is owned jointly by the SolarWind III Fund of Taaleri Energia, a co-investor of that fund, and KJK Fund III, which is managed by KJK Capital. It lies about 50 kilometres to the south of Tartu, and it was developed by Evecon, a Baltic renewable energy developer, in partnership with the French producer Corsica Sole. The Estonian contractor Smartecon is building it on a turnkey basis, while the battery equipment is being supplied by LG Energy Solution and the inverters by Power Electronics.
Jonathan Sistonen, who heads renewables and energy storage for the Nordics at AFRY, said that the company was glad to go on working with Taaleri on the project, and that it could now take what it had learnt in development into the construction stage. AFRY has said that it has worked on more than 1,000 BESS projects in the world, from feasibility studies and due diligence to owner's engineering and support in operation.
The developers and the contractor of Raudsepa have also been at work on other batteries in Estonia. Evecon and Corsica Sole, together with Mirova, had secured €85.6 million in January for the Hertz 1 and Hertz 2 batteries in Harju County, which are rated at 200 MW and 400 MWh in total. Smartecon, for its part, had carried out the network testing for the 21 MW/48 MWh battery of Sunly at the Raba energy park, which was commissioned in October.