Waaree Energies to develop solar and BESS in Maharashtra

Kaleeswari

Executive Summary

A PPA has been signed between Waaree Energies’ subsidiary Waaree Forever Energies and SECI for a 700 MW solar project integrated with a 700 MW/2,800 MWh energy storage system in Solapur, Maharashtra. The Ministry of Power has separately authorised the company to establish a 21-km, 400 kV transmission line connecting Salgar and Konhali villages.  

Snapshot 

  • Company: Waaree Energies Limited 

  • Subsidiary: Waaree Forever Energies 

  • Agreement with: Solar Energy Corporation of India (SECI) 

  • Project location: Solapur, Maharashtra, India 

  • Solar capacity: 700 MW 

  • Energy storage capacity: 700 MW/2,800 MWh 

  • Agreement announced: 20 November 2026 

Waaree Energies, a Mumbai-based solar module manufacturer, said its wholly owned arm, Waaree Forever Energies, has signed a Power Purchase Agreement (PPA) with the Solar Energy Corporation of India (SECI). The deal is for a 700 MW solar project that comes with a 700 MW/2,800 MWh energy storage system in Solapur, Maharashtra. The company shared this news on 20 November 2026, through a stock exchange filing. 

The plan puts power generation and energy storage together at one site. Under the SECI agreement, Waaree Forever Energies will build the storage facilities in Maharashtra.  

Separately, the Ministry of Power gave Waaree Forever Energies the go-ahead on 6 October 2026 to build an overhead transmission line. This line will provide connectivity to the proposed 700 MW solar plant. The approval came under Section 164 of the Electricity Act, 2003. 

The transmission setup will include a 21-km, 400 kV single-circuit overhead line, set on double-circuit towers. It will link the project's generation switchyard at Salgar village to the RGESL PSS4 generation switchyard at Konhali village. Both villages sit in Akkalkot taluka of Solapur district. 

The Ministry of Power has cleared the transmission line for 25 years. Still, the company has to get the needed permissions and clearances from the authorities before it starts installing anything. That covers approvals from local bodies, railway authorities, and highway authorities wherever they apply. 

The line will also need a nod from the electrical inspector or Chief Electrical Inspector before it can start running. These conditions are part of the authorisation. 

After the news came out, Waaree Energies shares closed 1.15% higher at INR 2,461 on the National Stock Exchange on 20 November 2026. However, the company’s shares had fallen 2.2% over the past month. They were down 16.7% during the year.

Evolta picks SolaX for 30 MWh microgrid BESS in Haiti

Intesa Sanpaolo lends €10 million to flow battery maker GES

Hanersun & Electrical One secure 45 MWh BESS deal in Hungary

ZE Energy acquires 59 MW/472 MWh BESS project in Italy

Energy Vault secures $78 million bridge loan for Sosa BESS