Standalone BESS operators in India have so far had only their contracts to rely upon when a DISCOM has paid late. Under a draft amendment from the Ministry of Power, they would be brought within the Late Payment Surcharge Rules, 2022, and would thus be given the deadlines, surcharges and payment security that generators already enjoy.
Amended rules: LPS Rules
New category: Storage providers
Payment window: 45 days
Surcharge premium: 5 points
Monthly increase: 0.5 point
Pumped hydro 2035-36: 630 GWh
BESS by 2035-36: 321 GWh
The Ministry of Power (MoP), an India-based federal ministry in charge of the electricity sector, has proposed to extend the Electricity (Late Payment Surcharge and Related Matters) Rules, 2022, to standalone energy storage systems. Their operators would then be protected against delayed payments by distribution companies (DISCOMs) in the same manner as generators, transmission companies and electricity traders already are.
The gap has arisen from the ownership of storage. Under Rule 18 of the Electricity Rules, 2005, the owner may be a generator, a transmission company, a DISCOM, a consumer or an independent company. A generator's system takes on the generator's legal status and is covered already, but a standalone provider has had only its contract to rely upon. The draft would therefore add a category of energy storage service provider for companies that sell storage as a service or supply power from storage and are not owned by any of the other four.
Such a provider would thereby gain the safeguards that were brought in during 2022 to stop the build-up of unpaid DISCOM dues. A bill is to be paid by the date in the power purchase agreement, or within 45 days if no date has been set. An overdue amount carries a surcharge of the one-year lending rate of the State Bank of India plus 5 percentage points, which rises by 0.5 percentage point for each month of delay. A DISCOM must also keep a letter of credit, and it is barred from the short-term market and the power exchanges once a bill has remained unpaid for two and a half months.
ESS projects need large investment upfront, which is recovered through payments over many years. Investors and banks will invest into such projects only if they are confident that these payments will be made on time.the Ministry of Power, Government of India
The ministry has tied the change to the investment that lies ahead. India's BESS capacity is projected to grow from 15 GWh in October 2026 to 321 GWh by 2035-36, and pumped hydro storage from 44 GWh to 630 GWh. The ministry expects that timely payment would draw that investment and lower the cost of financing, which could in time bring down the cost of storage.
The proposal has come only days after the Union Cabinet approved INR 14,500 crore of viability gap funding for 92 GWh of grid-scale storage, of which 30 GWh is meant for BESS. It may matter as much to projects already awarded, as Crisil Ratings has said that around 8 to 9 GWh of awarded BESS capacity could face a higher risk of delays, with LFP systems now quoted at around $70 to $75 per kWh.