Jupiter Power, a US-based developer of utility-scale BESS, has placed an order with Samsung SDI America for 16 GWh of lithium iron phosphate (LFP) batteries, which are to be supplied over three years from 2029. The batteries will be made in Indiana, and the order has raised its total with the South Korean manufacturer to about 27 GWh.
Order size: 16 GWh
Chemistry: LFP
Supply start: 2029
Supply period: Three years
Total orders: 27 GWh
Production site: Indiana
Value in KRW: Several trillion
Jupiter pipeline: 110 GWh
Samsung SDI, a South Korea-based battery manufacturer, has signed an agreement through its US subsidiary, Samsung SDI America, for the supply of LFP batteries to Jupiter Power, a US-based developer, owner and operator of utility-scale BESS. Under the agreement, which has been estimated to be worth several trillion Korean won, a total of 16 GWh of batteries will be delivered over three years, beginning in 2029, for the large-scale storage projects of Jupiter Power in the United States.
The batteries will be produced in Indiana, where the company has recently begun the mass production of LFP batteries. Samsung SDI has said that it is the only producer outside China of prismatic batteries for BESS in North America, and that it has also secured sources outside China for its key battery materials. Fabrice Hudry, President ESS of Samsung SDI America, said that the agreement reflected the competitiveness and the supply capability of the prismatic LFP batteries which the company produces in the US.
For Jupiter Power, the order follows an earlier deal with the same supplier, and its orders from Samsung SDI now amount to about 27 GWh in total. The developer, which is backed by Global Infrastructure Partners, a part of BlackRock, has 19.7 GWh of projects that are operating, under construction or committed, and a further 110 GWh in development across the country. According to Andy Bowman, its Chief Executive Officer, equipment that is made in the US is central to the way in which the company plans its build program and limits its risks.
SAMSUNG SDI’s LFP batteries, produced here in the U.S., strengthen our supply chain as we continue to deliver reliable power and capacity when and where the grid needs it most.Andy Bowman, Chief Executive Officer of Jupiter Power
The order also marks a change in the storage business of Samsung SDI, which has so far been built on batteries of the nickel cobalt aluminium (NCA) type and which now includes LFP batteries as well. In support of the LFP business, the company has been strengthening its supply chain through material supply agreements with Korean companies, including POSCO Future M and L&F.
The earlier BESS orders of Samsung SDI in the US have been for the NCA chemistry. In October, the company agreed to supply 1 GWh of its Samsung Battery Box 1.7 systems, which are made in Kokomo, Indiana, to Alpha Omega Power, and the delivery is due by the end of 2026. Jupiter Power, for its part, has also contracted with Peak Energy for up to 4.75 GWh of sodium-ion systems, which are to be deployed between 2027 and 2030.