Avantus signs PPAs for 3.2 GWh BESS and 800 MW Solar in US

Avantus has secured 20-year PPAs with PG&E for the Buttonbush solar and battery storage developments in California, with commercial operations expected in 2029. (Image Credit: Avantus)
Avantus has secured 20-year PPAs with PG&E for the Buttonbush solar and battery storage developments in California, with commercial operations expected in 2029. (Image Credit: Avantus)
Published on: 

EXECUTIVE SUMMARY

California-based Avantus has signed 20-year power purchase agreements with Pacific Gas and Electric Company (PG&E) for the Buttonbush 1A and 1B projects in Kern County. The projects combine 800 MW of solar capacity with 3.2 GWh of battery storage. Construction is scheduled for 2027, with commercial operations expected in 2029, subject to regulatory approval.

Avantus, a US-based renewable energy company that develops, owns and operates utility-scale BESS projects has signed 20-year power purchase agreements (PPAs) with Pacific Gas and Electric Company (PG&E) for the Buttonbush 1A and 1B solar and battery storage projects in western Kern County, California. Announced on 17 November 2026, the agreements cover a combined 800 MW of solar capacity and 3.2 GWh of battery storage. The projects are expected to generate enough electricity to meet the annual needs of approximately 381,000 homes.

Avantus is a US-based company that develops, owns and operates utility-scale solar and energy storage projects across California and the Desert Southwest. The company plans to own and operate both Buttonbush projects as an independent power producer (IPP).

The agreements are among the largest utility-scale solar and storage offtake deals signed in California to date. The battery systems will allow electricity generated during the day to be stored and supplied during evening hours, when solar generation falls and electricity demand increases.

Buttonbush 1A and 1B involve an estimated infrastructure investment of $3 billion in Kern County. Over their operating life, the projects are expected to generate hundreds of millions of dollars in local property tax revenue, which will support public services and infrastructure.

Construction is expected to begin in 2027, with commercial operations scheduled for 2029. The projects are expected to create approximately 900 union construction jobs, along with permanent jobs in operations and maintenance.

The projects will be developed on water-stressed farmland in Kern County. The use of this land will help meet California's groundwater requirements, while long-term lease agreements will provide farmers with a regular source of income. The arrangement will also preserve limited water resources for other agricultural activities.

Avantus already has solar and storage projects in Kern County. In July 2026, the company began commercial operations at Aratina 1, which has 200 MW of solar capacity and 500 MWh of battery storage. Its neighbouring Aratina 2 project is under construction and will add another 150 MW of solar capacity and 452 MWh of storage when completed. The project supported up to 300 jobs during peak construction.

PG&E said the Buttonbush projects would be among the largest clean energy resources in its portfolio. The utility expects the projects to help meet growing electricity demand across its service area over the 20-year agreement period.

The PPAs are subject to approval by the California Public Utilities Commission (CPUC). Avantus expects the projects to begin supplying electricity to California's grid in 2029.