NTPC Green Energy has awarded Pace Digitek, an India-based energy and telecom infrastructure company, an order worth INR 2,691 crore for a 600 MW/1.8 GWh BESS at the Khavda solar plant in Gujarat. Under the contract, which is the largest BESS order of the company so far, Pace Digitek will build the system and then operate it for 15 years.
Order value: INR 2,691 crore
Capacity: 600 MW/1.8 GWh
Blocks: Two
Location: Khavda, Gujarat
O&M term: 15 years
Completion: September 2027
Order book: INR 13,427 crore
BESS portfolio: 6.62 GWh
Pace Digitek, an India-based energy and telecom infrastructure company, has received a Letter of Award from NTPC Green Energy for a 600 MW/1.8 GWh BESS, which is to be built at the Khavda solar plant of NTPC REL in Gujarat. The order is worth INR 2,691 crore (about $287.3 million), including GST, and it covers both the engineering, procurement and construction (EPC) of the system and its operation and maintenance for a period of 15 years. It is, according to the company, the largest BESS order that it has secured to date.
The award is for two blocks, Block-01 and Block-02, each of which has a capacity of 300 MW/900 MWh. Both of the blocks form a part of Cluster-01 of a 3.3 GWh BESS project at the Khavda plant. Under the terms of the order, Pace Digitek will supply and integrate the battery systems, and it will also be responsible for their installation, testing and commissioning, as well as for the civil works. The project is to be completed by September 2027, as stated in the filing of the company.
In its announcement, the company has said that its standing as a Class-I Local Supplier was an important factor in the award. Under these criteria, a supplier must source at least 50% of the value of its goods, services and works in India. The company has also stated that its investments in localisation, which include 5 GWh of BESS manufacturing capacity in operation in India and an in-house facility for the fabrication of containers, have strengthened its position in the bidding.
As a Class-I Local Supplier under domestic value addition guidelines, this award highlights the crucial role of local content and domestic manufacturing in advancing India’s energy storage goals.Venugopalrao Maddisetty, Chairman and Managing Director of Pace Digitek
The award has also added to the order book of Pace Digitek. With this order, its cumulative order inflows for FY27 have reached INR 5,129 crore, and its total executable order book now stands at INR 13,427 crore. Its consolidated portfolio of BESS projects, meanwhile, amounts to 6.62 GWh, and it is spread across EPC contracts as well as build-own-operate (BOO) and build-own-operate-transfer (BOOT) projects.
The company has said that it is continuing to build its presence in the energy storage market of India through projects for central nodal agencies and state utilities. According to Maddisetty, Pace Digitek has invested in its manufacturing capacity ahead of demand, and the expansion of that capacity from 5 GWh towards 10 GWh is now under way, with the 10 GWh level targeted for the third quarter of FY27.