Kyon Energy begins commissioning of 203 MWh BESS in Germany

Kyon Energy's 100 MW/203 MWh Dahlem battery storage facility enters technical commissioning in Germany. (Image Credit: Kyon Energy)
Kyon Energy's 100 MW/203 MWh Dahlem battery storage facility enters technical commissioning in Germany. (Image Credit: Kyon Energy)
Published on: 

EXECUTIVE SUMMARY

The 100 MW/203 MWh Dahlem battery storage facility in Germany has entered technical commissioning following the energisation of its grid connections in August 2026. Developed by Kyon Energy, the project is undergoing electrical and control system testing ahead of commercial operation and forms part of a portfolio backed by Allianz Global Investors.

Kyon Energy, part of TotalEnergies Integrated Power Germany, has begun technical commissioning of its 100 MW/203 MWh battery energy storage system (BESS) in Dahlem, Germany. The company announced the development on November 24, 2026, marking the project's transition from construction to technical testing and verification. Kyon Energy develops battery storage projects, oversees their construction and manages their subsequent operation. The Dahlem facility is located in the Euskirchen district of North Rhine-Westphalia and is among Germany's largest battery storage projects approaching commercial operation.

The two grid connections serving the newly constructed substation were successfully energised in August 2026. Following their energisation, the battery storage facility entered the hot commissioning phase. During this stage, the electrical and control systems are being systematically tested and brought online. These include the substation, transformers, inverters, batteries, switchgear and control units.

The commissioning process also involves verifying the interaction between individual system components and their connection to the high-voltage grid under different operating conditions. Health and safety remain a central focus throughout the testing process. Once technical testing is completed, the facility will be ready for integration into the German power system.

The project is located near existing renewable energy and electricity infrastructure in Dahlem. The municipality already accommodates a large substation operated by Westnetz and several wind turbines, while additional photovoltaic installations are in the planning stages. The battery storage facility adds another component to the local energy infrastructure, bringing renewable electricity generation, grid connections and energy storage together within the same area.

Thomas Maubert, Managing Director of Kyon Energy, highlighted the importance of technical commissioning in preparing the facility for future operation. Dahlem Mayor Jan Lembach also welcomed the project's progress, noting the municipality's longstanding involvement in renewable energy development.

Kyon Energy developed the Dahlem project and managed its construction. The company will assume responsibility for operating the facility following technical and commercial commissioning. Dahlem follows the successful implementation of Kyon Energy's battery storage projects in Arnsberg, Schobüll and Faid during 2026.

The facility represents the company's fourth proprietary battery storage project approaching commercial operation. It also forms part of a portfolio of eleven battery storage projects across Germany in which Allianz Global Investors (AllianzGI) acquired a 50% stake in 2026.

The Dahlem project adds to Kyon Energy's growing portfolio of company-owned battery storage facilities in Germany. Its integration into the electricity system will support an energy infrastructure increasingly reliant on renewable power generation.