EXECUTIVE SUMMARY
The 240 MWh Afon Wysg 1 battery storage project at Uskmouth Sustainable Energy Park has received all batteries and key components. Ampeak Energy expects first energisation in November 2026 and commercial operation in Q1 2027. The company is also progressing a planned expansion to 480 MWh, with financial close targeted after the initial project becomes operational.
Click here for a quick project snapshot
UK-based Ampeak Energy Limited has completed the delivery of all batteries and key components for its 240 MWh Afon Wysg 1 (AW1) battery energy storage project at Uskmouth Sustainable Energy Park. The project is scheduled for first energisation in November 2026, followed by full commercial operation in the first quarter of 2027. Ampeak Energy is also progressing plans to expand the facility to 480 MWh, with financial close for the proposed expansion targeted shortly after the initial project becomes operational.
The company confirmed that all 55 batteries were supplied and delivered by e-STORAGE, part of Canadian Solar. e-STORAGE will also undertake commissioning activities. Principal contractor Jones Bros Civil Engineering UK has installed the batteries, 36 inverters, 18 twin skids and the main grid transformer.
Delivery of the major components was completed over 22 days. A 10-member Jones Bros delivery team, including a higher degree apprentice, coordinated transportation schedules and equipment deliveries with e-STORAGE. The operation involved handling equipment weighing nearly 3,000 tonnes in total.
The milestone followed completion of concrete foundations for the battery and power conversion system units, associated ducting and precast inverter troughs. Ampeak Energy has also reserved space between the batteries and completed foundations for the proposed expansion. This preparation is intended to enable additional capacity installation without repeating the initial groundwork.
Construction of the new on-site substation has been completed, alongside the installation of high-voltage cabling connecting the facility to national grid infrastructure. Approximately two-thirds of the existing power station export cable has been reused, reducing construction time and costs.
The project has incorporated measures to limit construction-related environmental impacts. Bulk aggregates were transported by rail to minimise heavy goods vehicle movements. Concrete recovered from earlier demolition activities was crushed and repurposed. An attenuation pond, fencing and landscaping have also been completed as part of the site's ecological enhancement plan.
Ampeak Energy CEO Designate David Taaffe confirmed that the next milestone will involve energising the batteries from the grid, followed by charge and discharge commissioning. Jones Bros Project Manager Gareth White highlighted the coordination required for sequential equipment installation and the recruitment of local workers.
Matt Paterson, Managing Director, EMEA, at e-STORAGE, identified system energisation and commissioning as the next stages. Ampeak Energy intends to pursue financial close for the 480 MWh expansion after AW1 begins commercial operation.