Battery delay pushes Kerala's 125 MW Mylatti BESS to February

Illustrative rendering of rows of white battery containers on red soil beside green trees.
Illustrative rendering of a KSEB battery storage site on laterite soil in Kerala.Image Credit: AI
Published on: 

Executive summary

The 125 MW BESS of KSEB at Mylatti in Kerala is expected to be completed by February 2027, and not in December, because its batteries will not leave China until 20 December. The batteries for the 30 MW Areekode project are already on their way, while a rise of up to 50% in lithium-ion prices has slowed the supply.

The Kerala State Electricity Board (KSEB), an India-based state-owned utility, is now likely to complete its 125 MW BESS at Mylatti by February 2027, and not in December, as had been targeted. The batteries for the project are scheduled to leave China on 20 December, and their late arrival has been named as the main obstacle, according to a report that was published by Kerala Kaumudi on 28 November.

The batteries for the smaller 30 MW project at Areekode are already on their way. Their container has left China and is expected to reach Mumbai within three weeks, after which it is to be carried to the site by road. Preparations have been made at Areekode so that the storage of power can begin soon after the batteries arrive, and the power transformer for the site was expected within two days.

Areekode is to become the second storage project in the state to come into operation. The first, a 15 MW project at Mulleria, has already been completed at a cost of about INR 70 crore. In all, six BESS projects are being built on KSEB land, and the other sites that are named in the report are Pothencode, Sreekandapuram and Brahmapuram.

Battery prices are also a part of the story. Lithium-ion batteries cost up to 50% more than before, the report says, so Chinese suppliers no longer want to deliver them on the old terms. That will push building costs up. Batteries from Europe or the United States are dearer still, and China supplies more than 90% of the batteries in the world.

The projects are now running behind the schedule that had been given earlier. In July, KSEB had told the State Electricity Regulatory Commission that five of them, namely Mylatti, Sreekandapuram, Mulleria, Areekode and Pothencode, were to be ready by October 2026. At that time, Mylatti was listed at 125 MW/500 MWh and Areekode at 30 MW/120 MWh.

The storage is needed so that the cheap solar power of the day can be used in the evening and at night. In July, when temperatures were high, the night-time demand in Kerala rose by 500 MW to 600 MW, and load had to be shed across the state, while the own generation of KSEB, at 21.02 million units, stood against a consumption of 90.45 million units. A larger BESS of 250 MW/1 GWh is also planned at NTPC Kayamkulam, for which the bids are due on 11 December.

Also Read
NGEL invites bids to build 250 MW/1 GWh BESS at Kayamkulam
Illustrative rendering of rows of white battery containers on red soil beside green trees.