MetaWealth secures a 100-MWh BESS project in Romania's Dolj County

Metawealth signed a purchase agreement for a standalone BESS in Romania's Dolj County.
A purchase agreement signed by MetaWealth for a 50 MW/100 MWh standalone BESS project in Romania's Dolj County, expanding its battery storage portfolio to 300 MWh. (Image credit: AI)
Published on: 

Executive Summary

By signing an agreement to acquire a 50 MW/100 MWh standalone BESS project in Romania's Dolj County, Meta Wealth plans an estimated €20 million investment. The acquisition increases its Romanian battery storage portfolio to 148 MW/300 MWh across three projects. Construction of the Dolj facility is scheduled to start in Q2 2027, with commercial operation expected in Q3 2027.  

MetaWealth, a European real asset investment platform, has secured its third battery energy storage system project in Romania. The company signed a purchase agreement on 4 November 2026 for a 50 MW/100 MWh standalone facility in Dolj County. The project is expected to require an investment of around €20 million. With this addition, MetaWealth’s total battery energy storage capacity in Romania now stands at 148 MW/300 MWh across three projects, all set to begin operation in 2027.  

The Dolj project is ready to build: the land is secured, the technical grid connection approval is issued, and the building permit is in hand. Its close location to a grid node is expected to lower connection costs and reduce risks.

Construction is scheduled to start in the second quarter of 2027 with commercial operation expected in the third quarter of the same year.  

MetaWealth’s portfolio in Romania includes the Dumbrava and Sânpaul projects. The Dumbrava project is currently under construction and is expected to start operating commercially in the second quarter of 2027.

In August, the company secured a €19 million financing package for Dumbrava, which includes about €10 million in seven-year debt from CEC Bank. Construction at Sânpaul is set to begin in the first quarter of 2027 with commercial operation expected in the third quarter of 2027.  

At the Dumbrava site Parapet Group is managing construction work. The main transformer, power conversion systems, and medium-voltage skids have already arrived at the Port of Constanța. Battery deliveries are expected between 20 November and 4 December 2026.  

MetaWealth has also started a divestment process for the Dumbrava project. This process will continue until its scheduled commercial operation date in the second quarter of 2027. The company has received six offers with more than twelve interested parties. The strategy is to develop the three projects to commercial operation before selling them.  

Future projects will remain in MetaWealth’s portfolio for energy arbitrage and long-term trading activities. Founder and CEO Michael Topolinski said the company plans to bring an additional 500 MWh into commercial operation in 2028. He added that investor demand for the bonds financing the storage projects has been very strong.

Moreover, Cernavodă Unit 1, about 10% of Romania’s power, goes offline in 2027 for a 32-month refurbishment, the adequacy study for Transelectrica says the standard may not be met in 2027, and Romania had about 2.31 GWh of storage in early October against an estimated 6,000 MWh needed in 2027.