EXECUTIVE SUMMARY
Philippine energy company Raslag Corp. has announced that its wholly owned subsidiary, Raslag Liwayway, Inc., received a Certificate of Authority from the Department of Energy for a solar power plant with battery energy storage in Nueva Ecija. The one-year authorization permits feasibility studies and the procurement of necessary development permits.
Click here for a quick project snapshot
Philippine energy company Raslag Corp. (ASLAG) has announced that its wholly owned subsidiary, Raslag Liwayway, Inc. (RLI), has received a Certificate of Authority (COA) from the Department of Energy (DOE) for the Raslag Liwayway Solar Power Plant with Battery Energy Storage System (BESS). The proposed project is located in Sta. Rosa, Nueva Ecija, Philippines.
The DOE issued the certificate on 14 October 2026, according to the company's disclosure dated 29 October 2026. The authorization designates Raslag Liwayway, Inc. as the exclusive solar energy developer for the project within the designated area.
Under the certificate, RLI is authorized to obtain the necessary permits and certifications for the exploration, development and utilization of solar energy resources. The company can also undertake reconnaissance activities and other work required for feasibility studies, as specified in its approved work program.
The Certificate of Authority remains valid for one year from its issuance date. Following this period, RLI may qualify to execute a Solar Energy Operating Contract, subject to compliance with the DOE's requirements.
The disclosure confirms the project's inclusion of battery energy storage alongside solar power generation. However, Raslag Corp. has not disclosed the proposed solar generation capacity, battery storage capacity, investment value or construction schedule.