EXECUTIVE SUMMARY
ABO Energy and Field have commissioned a 16 MW / 33 MWh stand-alone BESS in Waldkappel following around 8 months of construction. The project sold to Field in 2025 before construction begun. The BESS stabilizes grid frequency by providing Frequency Containment Reserve (FCR), intraday trading and peak supply. ABO Energy manages technical operations.
Click here for a quick project snapshot
Europe-based developer and operator of battery storage systems, ABO Energy and London-based energy infrastructure company, Field have commissioned a stand-alone battery energy storage system (BESS) in Waldkappel, Germany in March 2026 after approximately 8 months of construction. The project was developed by ABO Energy and sold to Field in the Q2 of 2025 prior to construction, forming part of Field’s expansion into the German energy storage market.
The Waldkappel facility has an installed capacity of 16 MW and an energy storage capacity of 33 MWh, enabling discharge duration of more than 2-hours. The system can store electricity equivalent to the overnight consumption of nearly 10,000 two-person households, supporting grid balancing requirements. It is the 4th stand-alone battery storage project delivered by ABO Energy in Germany and the first in its portfolio to exceed 2-hour full power delivery duration.
The project incorporates a modular rack-based system design rather than conventional containerized battery units. The racks are mounted on steel frames and were delivered to the site in a pre-assembled format, reducing on-site construction and installation timelines. Each rack includes an integrated thermal management and protection system, designed to maintain operational stability and system safety during performance cycles.
The BESS provides grid services including Frequency Containment Reserve (FCR), contributing to grid frequency stabilization. It also participates in intraday electricity trading and supports the supply of stored electricity during peak demand periods. These functions enable the system to manage fluctuations in renewable energy generation, particularly from variable sources such as wind and solar.
Field is developing a cross-border platform focused on battery storage and flexible energy systems across Europe, with projects in multiple core markets. The Waldkappel project represents its first operational asset in Germany and forms part of its strategy to establish a portfolio of transmission system operator (TSO)-connected battery storage assets in areas with identified grid requirements.
ABO Energy continues to provide technical management services for the facility, covering operational oversight and system performance. The project contributes to Germany’s expanding BESS capacity and reflects ongoing deployment of grid-scale storage systems supporting electricity system flexibility, short-duration balancing and market participation mechanisms.
Joachim Hundt, ABO Energy's Head of Cooperations in Financing & Sales, stated that the project supports investment opportunities for energy suppliers and funds, with private capital identified as a key factor in Europe’s energy transition. ABO Energy will provide technical management services for the plant.
Philip Hainbach, General Manager at Field, described Waldkappel as the company’s first project in Germany and noted its role in demonstrating rapid battery storage deployment. Luke Gibson, COO of Field, added that the project marks the initial step in building the company’s German portfolio, focusing on TSO-connected assets supporting grid operations and renewable integration.