Battery storage with a capacity of 500 MW and 1 GWh has been put into operation by MSEDCL, an India-based state-owned power distribution company, at 50 sites across Maharashtra. The batteries are charged with surplus solar power during the day, and they supply that power in the evening, when demand reaches its peak.
Click here for a quick project snapshot
MSEDCL, an India-based state-owned power distribution company, now has 500 MW of BESS in operation at 50 sites across Maharashtra, each of them rated at 10 MW. The systems can each supply power for two hours, so that they hold 1 GWh of energy between them. The company has said that no other distribution company in India has reached this scale in a decentralised network.
The power that the batteries store is generated under the Mukhyamantri Saur Krishi Vahini Yojana 2.0, a state scheme that supplies daytime solar power to agricultural pumps. About 7 GW of decentralised solar capacity has been commissioned under the scheme, and the surplus from those plants is now being stored during the day, so that it can be released in the evening, when demand is at its highest.
That evening supply has been the costly part of the day for the utility. Solar power is relatively cheap while the sun is up, but once generation falls away, power often has to be bought from the market at higher rates. In October, reduced rainfall that has been linked to El Niño made the weather hotter and lifted demand in Maharashtra, and the stored power has been used to meet the evening peak while reducing those purchases.
Lokesh Chandra, the Chairman and Managing Director of MSEDCL, who is also the Additional Chief Secretary to the Chief Minister, said that the batteries had been of particular use during the higher demand and the drought-like conditions in parts of the state. According to MSEDCL, the systems are also expected to be useful in summer, when demand usually rises.
More capacity is to follow. MSEDCL has planned BESS projects with a total power capacity of 750 MW and two hours of storage, or 1.5 GWh, and the remainder is expected to be commissioned by the end of December 2026. Projects with a further 4 GWh of storage are under development.
The utility has also been buying storage through tenders this year. In July, MSEDCL sought 2 GW/4 GWh of BESS under tariff-based global bidding, and under that tender, two Letters of Award for 900 MW/1.8 GWh were awarded to Oriana Power, for a project value of about INR 3,870 crore. In September, GK Energy also received a Letter of Award from MSEDCL for a 150 MW/300 MWh project in the state.