Near Carletonville, in the South African province of Gauteng, Mulilo has reached commercial and financial close on the 77 MW/308 MWh Leeuwpoort BESS. It is the first large-scale battery storage project in the province to have reached this stage, and it will provide storage capacity and ancillary services to NTCSA under a 15-year agreement.
Click here for a quick project snapshot
On 16 November, Mulilo, a South Africa-based renewable energy developer and independent power producer, announced that it had reached commercial and financial close on the Leeuwpoort BESS. The project, which has a capacity of 77 MW/308 MWh, is to be built near Carletonville, in the Merafong City Local Municipality of Gauteng, and it will be connected to the Midas Main Transmission Substation. According to the company, it is the first large-scale battery storage project in Gauteng to have reached financial close.
Leeuwpoort was awarded under Bid Window 2 of the Battery Energy Storage Independent Power Producer Procurement Programme (BESIPPPP). Once the plant is in operation, it will provide storage capacity and ancillary services to the transmission system under a 15-year power purchase agreement with the National Transmission Company South Africa (NTCSA). For its battery system, the project will use the Haohan, which is supplied by BYD Energy Storage.
The debt for the project has been provided by a consortium of three lenders, namely Absa Bank Limited, Nedbank Limited and Standard Bank of South Africa Limited. The close has also been supported by the shareholders of Mulilo, Copenhagen Infrastructure Partners (CIP) and Norfund, and the advisers on the transaction were Arup, Bastion, Bowmans, Deloitte, ENS, Fasken, Marsh and Pepper Tree Capital. However, neither the value of the debt nor a construction timetable has been disclosed.
Beyond its lenders and shareholders, the project has a strategic empowerment partner in Reatile Group, and a local community trust has been included so that the community will participate in it over the long term. Mulilo, as the lead sponsor, will also be responsible for construction management, asset management, the oversight of operations and maintenance, and social impact management throughout the life of the project.
Projects such as Leeuwpoort play a critical role in enhancing grid stability, unlocking network capacity, and improving energy security.
Jan Fourie, the CEO of Mulilo. Sunette Smith, the Chief Commercial Officer of Reatile Group, described the project as an important investment in the energy security of South Africa
With Leeuwpoort, Mulilo has now brought three BESS projects to financial close this year, as it follows the Mercury and Hartebeesfontein projects. At present, the company operates about 450 MW of renewable energy capacity, and it has a further 1,853 MW under construction, as well as more than 1 GW of projects that are advancing towards financial close. Its medium-term aim is to deliver 5 GW of renewable energy assets.