Rows of Tesla Megapacks at the Gorgas Battery Facility in Alabama. Image Source: Alabama Power
Projects

Alabama Power puts 150 MW Gorgas battery into service in Alabama

Karthik S Gannavaram

Executive summary

The Gorgas Battery Facility, which is the first utility-scale battery storage plant in Alabama, has begun to serve the customers of Alabama Power. It has been built with 92 Tesla Megapacks on the site of a former coal-fired plant, and it can store up to 150 MW. The facility entered service on 30 October, six months ahead of schedule.

  • Facility: Gorgas

  • Capacity: 150 MW

  • Duration: Two hours

  • Units: 92 Megapacks

  • In service: 30 October

  • Months early: Six

  • Homes served: 9,000

Alabama Power, a US-based electric utility, has put the Gorgas Battery Facility into service, and it has thereby brought the first utility-scale BESS plant in the state online. According to a report that the company published on 17 November, the plant can store up to 150 MW of electricity, which is enough to supply about 9,000 homes for up to two hours.

The facility stands on the site of the Gorgas plant, which had generated power for Alabama from coal for more than a century. It consists of 92 Tesla Megapacks, which together weigh 7.7 million pounds. In order to install them, the project teams logged more than 108,000 hours of work, and they laid nearly 35 miles of cable.

The plant began its service on 30 October, which was six months ahead of schedule. Its completion had previously been expected in 2027, and according to Alabama Power, it has been brought into service without an increase in customer rates.

Alabama Power has developed the facility partly in order to understand battery storage better, and to evaluate how the technology can support reliability as demand grows across the state. When demand changes, or when other resources are limited by weather, fuel availability or maintenance, the stored electricity will give the utility another option for serving its customers.

Battery storage gives us another tool to provide reliable energy. As Alabama continues to grow and energy demand increases, projects like the Gorgas Battery Facility help us understand how battery storage can work alongside our existing resources to support customers’ energy needs well into the future.
Brandon Dillard, Alabama Power’s senior vice president of Resource Strategy and Stakeholder Engagement

The experience that is being gained at Gorgas will be applied to future battery projects, among them the planned Clearview Solar and Battery Energy Storage Facility in Macon and Bullock counties. In the meantime, battery storage has become a part of Alabama Power's generation mix, alongside natural gas, coal, nuclear, hydropower, wind and solar.

ZE Energy acquires 59 MW/472 MWh BESS project in Italy

Energy Vault secures $78 million bridge loan for Sosa BESS

ADS-TEC Energy secures repeat 10 MWh BESS order from SWLB

KULR wins $14.8 million order for KULR ONE Max BESS in Japan

Swedish battery storage firm Polarium declared bankrupt