EXECUTIVE SUMMARY
Romanian renewable energy contractor Simtel has partnered with HiTHIUM to deploy 181.25 MWh of battery storage alongside 67.46 MWp of solar capacity in Sebeș, Romania. Developed by Windin Capital and El-Mor Group through HEPA Energy, the hybrid project will use 29 HiTHIUM ∞Power systems, with both companies supporting battery operations and maintenance.
BESS Supplier: HiTHIUM
EPC Contractor: Simtel
Project Developers: Windin Capital and El-Mor Group
Project Company: HEPA Energy
Location: Sebeș, Central Romania
Solar PV Capacity: 67.46 MWp
BESS Capacity: 181.25 MWh
BESS Product: HiTHIUM ∞Power 6.25 MWh
Number of BESS Systems: 29
HiTHIUM, a global energy storage solution, has partnered with Romanian renewable energy engineering and construction company Simtel to supply DC-side battery energy storage systems (BESS) for a hybrid renewable energy project in Sebeș, central Romania. Announced on 13 November 2026, the project is being developed by Windin Capital and El-Mor Group through their project company, HEPA Energy. The installation combines 67.46 MWp of solar photovoltaic capacity with 181.25 MWh of battery storage, making it one of Romania's largest hybrid renewable energy projects.
The storage installation will comprise 29 HiTHIUM ∞Power 6.25 MWh systems. The units are designed for integration with photovoltaic generation, with an operating lifespan engineered to align with solar power plants. HiTHIUM has developed the container configuration to improve compatibility with solar installations, optimise land utilisation and reduce long-term operating expenditure.
The systems operate at a noise level of 65 dB and incorporate a new environmentally friendly refrigerant and fully recyclable components. According to HiTHIUM, these design features are intended to support environmental compliance and improve operational efficiency throughout the project's lifecycle.
Simtel will provide operations and maintenance (O&M) services for the solar installation and work with HiTHIUM on maintaining the battery storage systems. HiTHIUM will support the project through its European spare-parts warehouses and third-party logistics arrangements.
Simtel has constructed more than 500 MWp of solar projects and owns and operates over 150 MWp of photovoltaic capacity. The company also maintains an existing portfolio of European solar O&M agreements covering approximately 450 MWp. The Sebeș installation will expand its involvement in integrated solar and battery storage projects.
The electricity generated and stored at the Sebeș facility will be supplied to Romania's national grid. The combined installation is intended to support electricity supply stability, strengthen energy security and facilitate greater integration of renewable generation.
HiTHIUM has also highlighted the safety engineering incorporated into its 6.25 MWh storage systems. During an independent open-door safety test conducted by UL Solutions in early 2026, the container was tested with its active fire suppression systems disabled. The doors remained open throughout the test, while fully charged neighbouring containers were positioned alongside it.
According to HiTHIUM, the tested container remained structurally intact, with no impact on adjacent units. The company said the results demonstrated the system's intrinsic safety design. The Sebeș agreement also introduces HiTHIUM's 6.25 MWh product to Romania's hybrid renewable energy market.