The Hopkins County project has added 200 MW of battery storage supporting dispatch flexibility and grid reliability during peak demand periods. Image Credit: Clearway Energy  
North America

Clearway completes USD 685 million solar-storage project in Texas

Team BESSNews

Clearway Energy Group has brought the Pine Forest Energy Center online in Hopkins County, Texas, comprising 300 MW of solar generation and 200 MW of battery storage. Representing a $685 million investment, the project enhances grid reliability, supports over 100,000 homes, and is backed by long-term virtual power purchase agreements with Dell Technologies and Universal Corporation.

PROJECT SNAPSHOT

FieldValue
ProjectPine Forest Energy Center
LocationHopkins County Texas USA
Developer / OwnerClearway Energy Group
TechnologySolar PV plus Battery Energy Storage
Solar Capacity300 MW
Storage Capacity200 MW battery
Total InvestmentUSD 685 million
Commercial OperationFebruary 2026
Construction ContractorBlattner Energy
OfftakersDell Technologies; Universal Corporation (VPPAs)