ZE Energy has acquired the 59 MW/472 MWh Magliano Alpi BESS project in Piedmont, Italy, from ReFeel New Energy. (Image Credit: ZE Energy) 
Business

ZE Energy acquires 59 MW/472 MWh BESS project in Italy

Prudhvi Rani Kona

EXECUTIVE SUMMARY

French electricity flexibility provider ZE Energy has acquired the fully permitted Magliano Alpi battery storage project from ReFeel New Energy in Italy. The 59 MW/472 MWh standalone facility will provide up to eight hours of storage and connect to the 132 kV grid. It is ZE Energy's third large-scale BESS project in Italy.

  • Company: ZE Energy

  • Seller: ReFeel New Energy

  • Project: Magliano Alpi BESS

  • Location: Magliano Alpi, Piedmont, Italy

  • Announcement Date: 23 November 2026

  • Power Capacity: 59 MW

  • Energy Storage Capacity: 472 MWh

  • Storage Duration: Up to 8 hours

  • Project Type: Standalone BESS

ZE Energy, a European electricity flexibility provider, has acquired the 59 MW Magliano Alpi battery energy storage system (BESS) project in the Piedmont region of northern Italy. The acquisition was announced on 23 November 2026. The project was purchased from ReFeel New Energy, an Italian renewable energy developer backed by Gresham House Europe, formerly SUSI Partners. It is ZE Energy's third large-scale standalone battery storage project in Italy, following Sessa Aurunca and Elena.

The Magliano Alpi project is fully permitted and ready for construction. It has a planned power capacity of 59 MW and an energy storage capacity of 472 MWh, providing up to eight hours of storage duration. The facility will connect to Italy's 132 kV high-voltage electricity network through an existing Terna substation.

The battery storage system is designed to support electricity supply and demand management in northern Italy. It will absorb electricity during periods of high generation and release stored power when demand increases or the electricity system experiences stress. The project will also support grid stability and help manage consumption peaks.

According to figures cited by ZE Energy from Terna, Italy's electricity demand exceeded 300 TWh in 2025, with net imports accounting for 15% of demand. Solar photovoltaic generation exceeded 44 TWh during the year, representing a 25% increase compared with 2024. The growing contribution from renewable energy has increased the need for storage systems capable of managing variations in electricity generation.

The Magliano Alpi acquisition expands ZE Energy's Italian portfolio into the northern part of the country. Its existing projects include Sessa Aurunca in central-southern Italy and Elena in southern Italy. The company said the geographic diversification will allow its storage portfolio to address different flexibility requirements and electricity markets.

ZE Energy develops, finances, constructs and operates standalone battery storage facilities and hybrid projects combining solar photovoltaic generation with batteries. The company has been active in electricity flexibility since 2020 and currently operates across France, Italy and Germany.

The acquisition also forms part of ZE Energy's strategy of purchasing permitted, ready-to-build storage projects. The company intends to apply its development, engineering, construction and operational capabilities to these assets.

ZE Energy has set a target of reaching 1.5 GW of installed capacity by 2030. The Magliano Alpi project adds another storage development to its European portfolio as the company continues expanding its activities in Italy.

Energy Vault secures $78 million bridge loan for Sosa BESS

ADS-TEC Energy secures repeat 10 MWh BESS order from SWLB

KULR wins $14.8 million order for KULR ONE Max BESS in Japan

Swedish battery storage firm Polarium declared bankrupt

PowerX & Averroes partner to pursue BESS sales in GCC region