EXECUTIVE SUMMARY
Greenvolt Power has secured €58.9 million in project finance from UniCredit Bank Hungary for the 99 MW/288 MWh Project Buj BESS in northeast Hungary. Under construction and scheduled for completion in Q1 2026, the project is expected to become Hungary’s largest battery energy storage asset, supporting grid flexibility and renewable energy integration.
Company: Greenvolt Power
Location: Northeast Hungary
Project: Project Buj
Capacity: 99 MW / 288 MWh
Project Finance: €58.9 Million
Greenvolt Power, the utility-scale development arm of Greenvolt Group, has secured €58.9 million (USD 64.2 million) in project finance facilities to support the construction, operation, and maintenance of the 99 MW/288 MWh Project Buj battery energy storage system (BESS) in northeast Hungary. The finanacing has arranged with UniCredit Bank Hungary.
The project is under Construction, with completion scheduled for the first quarter of 2026. Once operational, the Buj facility is expected to be the largest battery energy storage asset in Hungary in terms of installed capacity, providing grid flexibility and supporting renewable energy integration into the national power system.
João Manso Neto, CEO of Greenvolt Group, stated that battery storage provides system flexibility required to support higher renewable penetration, and that the financing aligns with Greenvolt’s expansion of storage assets across European markets.
Balázs Toldi, Head of Corporates Division at UniCredit Bank Hungary, noted that predictable energy sources are important for Europe’s power system, and that the transaction enables UniCredit to participate in this development.
László Lakos, Director of Structured Finance at UniCredit Bank Hungary, said the financing of the Buj project supports Hungary’s energy transition and extends UniCredit’s existing partnership with Greenvolt across multiple assets and regions.
Adrian Góralski, Director of M&A and Project Finance at Greenvolt Power, stated that Greenvolt and UniCredit Bank Hungary structured a project finance solution aligned with the technical and operational requirements of Project Buj.